Article on "DOCTRINE OF IMPOSSIBILITY" by Aadya Chaudhary




By AADYA CHAUDHARY

COURSE: BA.LLB (Hons.)

SEMESTER: VII

COLLEGE NAME: VIVEKANANDA INSTITUTE OF PROFESSIONAL STUDIES, GGSIPU

 

DOCTRINE OF IMPOSSIBILITY

                                                     

Before diving directly into the concept of doctrine of impossibility, let’s first look into the definition of a contract as this doctrine has its roots in the Law of Contracts 1872[1] which states that a valid contract is an agreement to be fulfilled by the parties to the contract and it is also imperative that such a contract must be capable of being performed. Herein, we can make out from the definition itself that for the completion of the contract there is prior and subsequent condition attached to it which decides the performance of the contract to be complete or not.

Let’s assume A and B. A is the seller of the goods and B is the buyer. Until B makes the payment to A for the goods, A will not dispatch the goods. The fact that to get the goods B needs to make the payment and delivery of the goods is dependent upon that prior condition is what is makes a valid contract.

But what if the condition attached to the contract becomes impossible to perform in future so as to make the contract complete and valid?

This issue is discussed in Section 56 of the Indian Contract Act, 1872 enunciates the doctrine of impossibility in it and states that: “an agreement to do an act impossible in itself is void”.

This is the basic introduction of this doctrine, where sometimes the performance of a contract is or becomes impossible due to its own nature or due to some circumstances which are beyond the control of the parties (ultra vires) which renders the performance of contract impossible and the purpose of the contract ceases to subsist.Doctrine of impossibility, in a nutshell refers to frustration of contracts on the ground that the party to the contract is unable to discharge his part of the obligation due to impossibility of performance of such a contract.

This amounts to discharging parties of their obligation.

This frustration is due to the unforeseen situations where it becomes impossible for a party to a contract to perform the obligations under it.In addition to this it also talks about a situation in which an act becomes impossible/unlawful or illegal,after the making of the contact. A contract is said to have been ‘frustrated’ if the performance of such a contract becomes impossible/unlawful to be performed.

For instance look at these illustrations:

a. “A agrees with B to discover treasure by magic” is void.

b. “A contracts to act at a theatre for six months in consideration of a sum paid in advance by B. On several occasions A is too ill to act. The contract to act on those occasions becomes void.”

In both the examples it’s impossible for the party to the contract to perform the contract.

SALIENT FEATURE OF DOCTRINE OF IMPOSSIBLITY

·         There must be a valid contract & in existence between the two parties;

·         There must be a part of the contract which is still remaining  to be performed;

·         That part of the contract, which is still to be performed, should become impossible/unlawful/illegal;

·         That the impossibility should be by reasons of some event which was unseen by the promisor.

 

TYPES OF IMPOSSIBILITY

The section includes about two types of Impossibilities

·         Initial Impossibility 

·         Subsequent Impossibility.

Initial impossibility implies that the impossibility should be in existenceat the time of the formation of the contract which might be known or unknown to the party.

If it is known to the party then the agreement is void ab initio. For example, “discovering treasure through magic.”

In case of Subsequent Impossibility, the performance of the contract is possible at the time of when agreement was made, but subsequently due unforeseen and uncontrollable change in the circumstances, have subsequently become impossible/unlawful or illegal to perform.

 For example, A agreed to sell his house to B. Later on the house was acquired by government. The contract becomes void on the ground of impossibility and A is discharged of his obligation to perform the duty to deliver his house to B

 

Note:  Performance cannot be excused on these ground (no supervening impossibility)

It must be noted that doctrine of impossibility will not apply to cases where the excuse for non-performance is merely based on the fact that the act was inconvenient or

·         The reason of commercial impossibility, i.e. expectation of higher profit is not achieved or is profitless,

·         Wherethe necessary raw material is available at very high price and hence the fact that it’sexpensiveand hence party is unable to fulfil the contract.

 Even if performance is impossible, a party may not be able to use the doctrine of impossibility as a defense to non-performance if the party where he:

  1. knew of the facts, at the time the contract was being  executed, that made performance of contract impossible;
  2. assumption of  the risk of impossibility; or
  3. could have acted in such a way as to prevent the event of performance of the impossible

 

CAUSES OF SUSEQUENT FRUSTRATION

 

·         Destruction of subject-matter of contract:
Where the subject matter of a contract is destroyed after the contract is made without any fault of the parties, the contract is discharged and no party is liable.[2]

·         Death or personal incapacity of the party:

If the performance of the contract was dependent upon any personal skill, qualification or personal ability of the promisee then such contract is frustrated on the events of death, incapacity or illness of the party who promised the fulfilment of that condition. The party to contract is discharged from performing his duty thereafter. A contract which is made for personal service cannot be performed by any agent or a legal representative.

·         Non-occurrence of contemplated event:


If the event which was expected to happen and that event is the foundation of the contract, is cancelled then that contract becomes void on the ground of frustration.[3]

·         Government, Administrative or Legislative intervention:
Sometimes, a contract is lawful at the time of its making but it may become unlawful due to a subsequent change in law or governmental policy. The obligation  is discharged by impossibility of performance.

·         Intervention of War:


If a war is declared after the formation of a contract; all pending contracts with the residents of enemy country is either suspended or declared as void. If war is of a short duration, it may be revived after the end of the war. However, if the war continues for a long period, contract will be discharged on the ground of impossibility

 

EFFECTS OF SUPERVENING FRUSTRATION

·         Contract becomes void.

·         Restoration or refund of benefit received.

·         Innocent promisee entitled to compensation.

 

FORCE MAJEURE

The term force majeure means an unavoidable accident or a chance occurrence. This clause is included in a contract to avoid uncertainties when any supervening event occurs and parties cannot be blamed. However, even if, this clause provides certainty to the contract it is not guaranteed that it will cover all supervening events. Due to COVID-19 pandemic accompanied by social distancing, quarantines, mass closings of business, etc., have hampered many pre-pandemic contractual obligations difficult or impossible to perform. In such a situation force majeure clause may excuse certain type of contractual performance and might mitigate some economic losses.

However, if force majeure clause fails to provide the desired relief then in such a situation, businesses may be forced to rely on the barely used legal doctrine of impossibility as defense against difficult pre-crisis contractual obligations. This may be applied where contract signed ceases to exist due to unforeseeable supervening event without the fault of either party.

INDIAN CASE LAWS

Satyabrata Ghose v Mugneeram Bangur and Company &Anr. AIR 1954 SC 44

Facts:

The defendant company launched a scheme to develop the land into a housing colony. The plaintiff was granted a plot on payment of advance money. The company committed to constructing the roads thereby making it suitable for residential purposes. The purchaser was to pay the remaining amount to complete the conveyance. Meanwhile, a large area of the land was taken over by the State during the Second World War for war purposes. The company attempted to revoke the contract on the ground of subsequent impossibility.

Held: The court dismissed the defendant’s suit. The requisition orders were temporary in nature and no deadline was mentioned in contract for construction. However, it was obvious for some restrictions to be in effect during the war, thereby causing delay in the project. Therefore, this delay doesn’t affect foundation of the contract.

Sushila Devi vs. Hari Singh, AIR 1971 SC 1756

This case is of This was a case of lease of property, which after the unfortunate partition, the property in dispute, situated in Gujranwala, and went onto the side of Pakistan, therefore making the terms of the agreement impossible.

In this case it was observed that the impossibility viewed by section 56 of the Contract Act is not limited to something which is not humanely possible. This was a case of lease of property, which after the unfortunate partition, the property in dispute, situated in Gujranwala, and went onto the side of Pakistan, therefore making the terms of the agreement impossible.

 

ENGLISH CASE LAWS

The origin of Doctrine of Impossibility is closely related to the English Rule: Subsequent Impossibility of performance cannot be a valid defense in cases of breach of an obligation under the contract. This rule was laid down in Paradine vs. Jane 82 Eng.Rep. 897(1647). So, before we dwell into the rationale of a judgment let’s have a look on the facts of the case: Paradine (Plaintiff) sued Jane (Defendant) under a lease for three years for unpaid rent. Defendant pleaded that due to invasion by the German Prince; he was forced out of possession and therefore he was unable to take the benefits. So, he refused to pay Plaintiff rent for the duration he was forced out.

However, the court gave judgment in favour of the Plaintiff and the defense was not held valid; as obligation under the contract was absolute with no exceptions. The judge held that liability under the contract should be followed under all circumstances.

This Doctrine of Impossibility was evolved as a reflection of the aforementioned case. There were cases where the contract couldn’t be performed due to circumstances through no fault of the defendant, and the rigidity of the English rule was found to be unreasonable, unfair, therefore an exception to the rule was need of the time.

 

CRITICAL ANALYSIS& CONCLUSION

An agreement which is enforceable in the court of law is known as contract. Contract also regulates the transfer of risk which is inherent in any contractual relationship. However, doctrine of impossibility comes into the picture where one party fails to perform his part of the obligation because of any subsequent event which was unforeseeable or if one of the party had prior knowledge that contract entered into is void ab initio which renders it impossible.It is a well settled law that the contract becomes impossible to perform only when the foundation or the genesis for which the contract was made becomes impossible to perform and not otherwise.

If the contract is frustrated because of the reason of subsequent events such as destruction of subject matter, death or incapacity, change in legislation or intervention of war then, it will work as solid defense.

 For a striking difference and to understand the grounds more clearly we can see that the court excused the defendant to perform his part of the obligation in the case of Krell vs. Henry and upheld that doctrine of impossibility was applicable very much whereas if we see the Indian case of Satyabrata vs. Mugneeram there the court dismissed the excuse of the defendants suit and it was held that delay in construction doesnt affect the foundation of the contract and hence not impossible to perform and therefore doctrine of impossibility was not applicable in the latter case.
The basic functionary of law is to impart justice and as the society changes due to new emerging needs and wants, law has taken the shape of being dynamic to serve and resolve the issue to anyone and everyone.

This doctrine came into being to resolve the issue

At the end, Indian judiciary has to put forward through trial and error, the test of foreseeability before giving the final verdict to impart effective justice to the plaintiff.

 


[1]Paradine vs. Jane 82 Eng.Rep. 897(1647)

[2]Taylor vs. Caldwell, (1863, 3 B & S 826)

[3]Case: Krell vs. Henry (2 K.B. 740, 1903)